Powerful winch solutions for extremely heavy-duty work
To ensure controlled extraction and precise positioning of these immense structures, Hydrauvision deployed its HW30CT winches. These systems are known for their reliability, consistent pulling performance and robust design, making them ideal for projects where absolute accuracy is essential.
For two intensive weeks, our team was on-site to oversee the complete winching operation. Their expertise, flexibility and close coordination with all executing parties ensured the successful completion of the first phase.
HydrauWinch 30 CT Specifications:
- Versatile winch for tugger applications
- Speed of 2.5 metres per minute
- Remote operation
- Real-time force measurement with load pins integrated into the foundation
- Offshore-certified lifting points in accordance with DNV 2.7-3
More information about the HydrauWinch 30 CT can be found in the datasheet.
A Remarkable Operation Along the Weser
The tunnel elements were subsequently towed along the Weser to the Industriehafen in Bremen. This impressive journey of nearly 60 kilometres attracted wide attention, including coverage by local media.
As the next phases are expected to begin in approximately eight to ten months, provided everything proceeds according to plan, Hydrauvision will again be ready on-site. A total of six tunnel elements will be winched and relocated, representing a significant logistical and technical challenge to which we contribute with dedication and enthusiasm.
Proud of Our Contribution and Collaboration
This project reflects the core values of Hydrauvision: technical strength, reliability and continuous innovation in heavy-duty equipment for international infrastructure projects. We are proud of our team, our Rental solutions and the strong cooperation with our valued partners.
Watch the impressive video report of the transport, showcasing our winches in action:
Commissioned by Immontec
Photography: Van der Kloet